Thursday, October 11, 2012

Frames Scheduled...but windows arrived first!!

Frames have been scheduled to be delivered by end of this week.

Unfortunaely, there was a 2 week delay in getting the frames, due to some issues at the manufacturer.. (high demand??).....

Funny that, our window and stacker doors came in a week before the frames.

Sad to see it dirty and copping a lot of dust. Our SS assured us it will be clean prior to installation.





Random shots

Decided to head out to our site and check if there had been any changes.

Guess not as we are waiting for the frames to be delivered.

So decided to take some pictures.

Front


 Side Slab


Taking advantage of the iPhone 5 and panoramic feature...

Views of the area from the side




Tuesday, October 9, 2012

Slab and drainage

We now have Slab!!

The piping along side the slab has also been done.

Thought they would had this done prior to the slab.




Friday, October 5, 2012

Friday, September 28, 2012

Wednesday, September 26, 2012

Excavation

As promised by our site supervisor, the work has started!!

Sunday, September 16, 2012

Yellow pegs

Surveyor has inspected our site and yellow pegs are down.


Something is happening...