Monday, November 12, 2012

It's Brick time!

Finally, the frames have completed and the bricks have been scheduled to be layed.

Most importantly, bricks have been delivered.

Boral Grays Point:

Boral Render brick:

Randoms

It has been awhile since we have posted our progress.

Roof frames are up!


Long hallway:


The first level:








Friday, November 2, 2012

first level UP! Already...

It appears that our SS is keeping us smiling.

The first half of the first level frames are up aswell as the steel support beams and floorboards.

Puzzle is getting close to a picture.




Monday, October 29, 2012

Ground level frames UP!

We are again excited.

Visited our site in the morning to see a few tradies putting the puzzle together on the groud level.


Rear stacker right door.



Splashback Kitchen window. 3.5 wide


Pantry and fridge cut out.


Computer nook and hallway (right)


Hallway and theatre (right)

Inside theatre room with recess for media area.


Right of theatre to stairway

Family room high slim window



Floorboards and windows in our garage

Slab Afresco. Left stacker door opening from our lovely kitchen.

Right stacker door. Best view for the portaloo...:P


Dirty windows and doors :(

Thursday, October 25, 2012

Frames....finally!! Ground level

Yes and finally,  2 weeks have gone by and ground level frames have been delivered.





Tuesday, October 23, 2012

Termites uninvited

After almost 2 weeks of patiently waiting for our frames, we decided to take a trip to our site.

To our amazement, termite barrier has been attached to our slab. Minus the afresco area.

Something is happening yet again.



Thursday, October 11, 2012

Frames Scheduled...but windows arrived first!!

Frames have been scheduled to be delivered by end of this week.

Unfortunaely, there was a 2 week delay in getting the frames, due to some issues at the manufacturer.. (high demand??).....

Funny that, our window and stacker doors came in a week before the frames.

Sad to see it dirty and copping a lot of dust. Our SS assured us it will be clean prior to installation.