Monday, October 29, 2012

Ground level frames UP!

We are again excited.

Visited our site in the morning to see a few tradies putting the puzzle together on the groud level.


Rear stacker right door.



Splashback Kitchen window. 3.5 wide


Pantry and fridge cut out.


Computer nook and hallway (right)


Hallway and theatre (right)

Inside theatre room with recess for media area.


Right of theatre to stairway

Family room high slim window



Floorboards and windows in our garage

Slab Afresco. Left stacker door opening from our lovely kitchen.

Right stacker door. Best view for the portaloo...:P


Dirty windows and doors :(

Thursday, October 25, 2012

Frames....finally!! Ground level

Yes and finally,  2 weeks have gone by and ground level frames have been delivered.





Tuesday, October 23, 2012

Termites uninvited

After almost 2 weeks of patiently waiting for our frames, we decided to take a trip to our site.

To our amazement, termite barrier has been attached to our slab. Minus the afresco area.

Something is happening yet again.



Thursday, October 11, 2012

Frames Scheduled...but windows arrived first!!

Frames have been scheduled to be delivered by end of this week.

Unfortunaely, there was a 2 week delay in getting the frames, due to some issues at the manufacturer.. (high demand??).....

Funny that, our window and stacker doors came in a week before the frames.

Sad to see it dirty and copping a lot of dust. Our SS assured us it will be clean prior to installation.





Random shots

Decided to head out to our site and check if there had been any changes.

Guess not as we are waiting for the frames to be delivered.

So decided to take some pictures.

Front


 Side Slab


Taking advantage of the iPhone 5 and panoramic feature...

Views of the area from the side




Tuesday, October 9, 2012

Slab and drainage

We now have Slab!!

The piping along side the slab has also been done.

Thought they would had this done prior to the slab.