Building Timeline


10 Oct 2012 - Progress Payment - Slab - 25%
08 Oct 2012 - Plumbing & Draining connections
04 Oct 2012 - Slab Poured, Official Rawson sign went up on the fence
03 Oct 2012 - Wafflepods completed
02 Oct 2012 - Plumbing completed - Wafflepods delivered
01 Oct 2012 - Labour day (Lost one day)
27 Sep 2012 - Piers & Formwork
26 Sep 2012 - Site fence went up and port-a-loo delivered
25 Sep 2012 - START DATE site excavation work (cut & fill)
21 Sep 2012 - Contact with Site supervisor
20 Sep 2012 - Site pegs
19 Sep 2012 - Construction Certificate Issued
18 Sep 2012 - Site supervisor appointed picked up our file
17 Sep 2012 - Waterboard approval received.
11 Sep 2012 - Formal approval of Construction Loan.
06 Sep 2012 - Waiting for waterboard approval to issue construction certificate
05 Sep 2012 - Received Council approval conditions variation to sign off (Variation #12)
03 Sep 2012 - Air conditioning issue resolved with Rawson
31 Aug 2012 - Received Council approved plans and documentation
27 Aug 2012 - Signed building contract. Received electrical variations to sign off (Variation #11).
22 Aug 2012 - DA approved. Conditional of air conditioning review
15 Aug 2012 - Received colour variations to sign off (Variation#9)
14 Aug 2012 - Electrical consultation
09 Aug 2012 - Loan paperwork submitted
08 Aug 2012 - Building contract received
25 Jul  2012 - Received colour variations to sign off (Variations#7&8)
16 Jul  2012 - Tender Expired. Extended without issues
11 Jul  2012 - Land Settlement. DA re-submitted to council for approval
05 Jul  2012 - Council returned DA due to lack of land ownership documents required :(
03 Jul  2012 - Land is registered! Settlement booked for 11th July.
26 Jun  2012 - Colour consultation
22 Jun  2012 - Council DA delays as land is not registered.
18 Jun  2012 - DA Plans, External Colours & Landscape plans submitted to Council.
17 Jun  2012 - Second installment paid
15 Jun  2012 - Amended DA plans received for approval (Issue C)
13 Jun  2012 - More variations (Variation# 6)
04 Jun  2012 - Received final Landscape plans for sign off
31 May 2012 - DA Plans received for approval (Issue B)
30 May 2012 - Received more variations to sign off (Variation #5)
27 May 2012 - Finalised external colours
24 May 2012 - Received preliminary landscape plans for review
22 May 2012 - Final plans received and engaged in landscape architect services
18 May 2012 - Received additional variations to sign off (Variation #4)
01 May 2012 - Received external variations to sign off (Variation #3)
27 Apr 2012 - Meeting with CSO to go through changes to check plans
24 Apr 2012 - First draft of check plans received (Issue A)
04 Apr 2012 - Colour pack received
26 Mar 2012 - Received tender variations to sign off (Variation #1)
26 Mar 2012 - CSO assigned
12 Mar 2012 - Contracts exchanged on land
15 Mar 2012 - Signed Tender, first installment paid
09 Mar 2012 - Tender received from builder
25 Feb 2012 - Initial appointment with Builder
25 Feb 2012 - Holding fee paid to Urban Land Housing on block of land